Timetable

Due to issues raised during the scoping period and public meetings, additional studies were needed and the timetable was delayed.

In addition, issues with the California State Budget in 2008-2009 have caused many funds to be temporarily frozen. This has resulted in additional work delays and thus schedule delays.

The following is the revised tentative timetable for the project:  

Task

Completion Date

Background reports, initial studies , base maps:

Initial site surveys and baseline geomorphic monitoring

Creation of base maps

Watershed Assessment Report for the Upper Reaches of the Upper Truckee River (SH&G, October 2004) .

Riparian Ecosystem Restoration Feasibility Report (River Run, March 2006).

Monitoring and studies

Completed

Completed

Completed

Completed

 

Completed

2005-ongoing

 

First draft of conceptual planning for river and golf course.

 

Completed

 

NOP NOI issued, public scoping meetings , (begin EIR EIS process)

 

 

Sept-Oct 2006

 

Newsletter # 1

 

Public workshop held (Summary of results).

 

 

Feb 8-9, 2007

 

Newsletter # 2

Nov 2007

 

Additional studies conducted (incl. Economic report )

Public site walks

Alternatives description revision/update

Environmental Analysis

 

Spring-Summer 2008

Summer 2008

Fall 2008

Spring–Summer 2009

 

 

News Notes update on project
   

Draft EIR/EIS Released

August 2010

 

Public Information Meeting/ Draft EIR/EIS Review

 

September 2010

 

Final EIR/EIS Issued (Response to Public/Agency Comments)

 

To be determined

 

General Plan Amendment PRC Hearing

 

To be determined

 

Final EIR/EIS Certified, Project Decisions (CEQA NOD, NEPA ROD)

 

To be determined

 

Depending on outcome of the EIR/EIS, the following additional phases MAY take place:

 

 

Final Designs (plans and specifications).

 

Fall 2011

 

Permits (regional water board, El Dorado County, California Department of Fish and Game, Tahoe Regional Planning Agency).

 

Spring 2011

 

First Phase Construction

 

2012

 

Additional Phases Construction

 

Additional 2 - 4 years