Timetable
Due to issues raised during the scoping period and public meetings additional studies were needed and the timetable has been delayed. The following is the revised tentative timetable for the project:
Task |
Completion Date |
Background reports and initial studies:
- Initial site surveys and baseline geomorphic monitoring
- Creation of base maps
- Watershed Assessment Report for the Upper Reaches of the Upper Truckee River (SH&G, October 2004) .
- Riparian Ecosystem Restoration Feasibility Report (River Run, March 2006).
|
Completed
Completed
Completed |
First draft of conceptual planning for river and golf course. |
Completed |
Newsletter #1 |
January 2007 |
Public workshop held (Summary of results). |
February 8-9, 2007 |
Environmental documents (EIR/EIS), General Plan amendment, pre-project monitoring and required studies. |
April 2006 to summer 2008 |
Onsite Data Collection |
2005-ongoing |
Interagency Meeting |
Summer 2006 |
NOP/NOI Issued |
September 2006 |
Public Scoping Period |
September – October 2006 |
Environmental Analysis |
Fall 2006 – Spring 2008 |
Public Information Meeting |
February 2007 |
Newsletter #2 |
November 2007 |
Additional Pre-project monitoring and data collection |
Summer 2007 |
Economic Study |
Fall 2007 |
Draft EIR/EIS Released |
Spring 2008 |
Public Information Meeting/ Draft EIR/EIS Review |
Summer 2008 |
Interagency Meeting |
Summer 2008 |
Final EIR/EIS Issued (Response to Public/Agency Comments) |
Fall 2008 |
General Plan Amendment PRC Hearing |
Fall/Winter 2008 |
Final EIR/EIS Certified, Project Decisions (CEQA NOD, NEPA ROD) |
Winter 2008 |
Depending on outcome of the EIR/EIS, the following additional phases MAY take place: |
|
Final Designs (plans and specifications). |
Fall 2009 |
Permits (regional water board, El Dorado County , California Department of Fish and Game, Tahoe Regional Planning Agency). |
Spring 2010 |
First Phase Construction |
2010 + |
Second Phase Construction |
2010 to 2011 |
Post Project Monitoring |
2011 to 2015 |