Due to issues raised during the scoping period and public meetings additional studies were needed and the timetable has been delayed. The following is the revised tentative timetable for the project:  

Task

Completion Date

Background reports and initial studies:

  1. Initial site surveys and baseline geomorphic monitoring
  2. Creation of base maps
  3. Watershed Assessment Report for the Upper Reaches of the Upper Truckee River (SH&G, October 2004) .
  4. Riparian Ecosystem Restoration Feasibility Report (River Run, March 2006).

 

Completed

 

Completed

 Completed

 

First draft of conceptual planning for river and golf course.

 

Completed

 

Newsletter #1

 

January 2007

 

Public workshop held (Summary of results).

 

February 8-9, 2007

 

Environmental documents (EIR/EIS), General Plan amendment, pre-project monitoring and required studies.

 

April 2006 to summer 2008

 

Onsite Data Collection

 

2005-ongoing

 

Interagency Meeting

 

Summer 2006

 

NOP/NOI Issued

 

September 2006

 

Public Scoping Period

 

September – October 2006

 

Environmental Analysis

 

Fall 2006 – Spring 2008

 

Public Information Meeting

 

February 2007

 

Newsletter #2

 

November 2007

 

Additional Pre-project monitoring and data collection

 

Summer 2007

 

Economic Study

 

Fall 2007

 

Draft EIR/EIS Released

 

Spring 2008

 

Public Information Meeting/ Draft EIR/EIS Review

 

Summer 2008

 

Interagency Meeting

 

Summer 2008

 

Final EIR/EIS Issued (Response to Public/Agency Comments)

 

Fall 2008

 

General Plan Amendment PRC Hearing

 

Fall/Winter 2008

 

Final EIR/EIS Certified, Project Decisions (CEQA NOD, NEPA ROD)

 

Winter 2008

 

Depending on outcome of the EIR/EIS, the following additional phases MAY take place:

 

 

Final Designs (plans and specifications).

 

Fall 2009

 

Permits (regional water board, El Dorado County , California Department of Fish and Game, Tahoe Regional Planning Agency).

 

Spring 2010

 

First Phase Construction

 

2010 +

 

Second Phase Construction

 

2010 to 2011

 

Post Project Monitoring

 

2011 to 2015

 

 

 