Timetable
Due to issues raised during the scoping period and public meetings, additional studies were needed and the timetable was delayed.
In addition, issues with the California State Budget in 2008-2009 have caused many funds to be temporarily frozen. This has resulted in additional work delays and thus schedule delays.
The following is the revised tentative timetable for the project:
Task |
Completion Date |
Background reports, initial studies , base maps:
Initial site surveys and baseline geomorphic monitoring
Creation of base maps
Watershed Assessment Report for the Upper Reaches of the Upper Truckee River (SH&G, October 2004) .
Riparian Ecosystem Restoration Feasibility Report (River Run, March 2006).
Monitoring and studies |
Completed
Completed
Completed
Completed
Completed
2005-ongoing |
First draft of conceptual planning for river and golf course. |
Completed |
NOP NOI issued, public scoping meetings , (begin EIR EIS process)
|
Sept-Oct 2006
|
| Newsletter # 1 |
|
Public workshop held (Summary of results).
|
Feb 8-9, 2007
|
Newsletter # 2 |
Nov 2007 |
Additional studies conducted (incl. Economic report )
Public site walks
Alternatives description revision/update
Environmental Analysis |
Spring-Summer 2008
Summer 2008
Fall 2008
Spring–Summer 2009 |
|
|
| News Notes update on project |
|
| |
|
Draft EIR/EIS Released |
August 2010 |
Public Information Meeting/ Draft EIR/EIS Review |
September 2010 |
Final EIR/EIS Issued (Response to Public/Agency Comments) |
To be determined |
General Plan Amendment PRC Hearing |
To be determined |
Final EIR/EIS Certified, Project Decisions (CEQA NOD, NEPA ROD) |
To be determined |
Depending on outcome of the EIR/EIS, the following additional phases MAY take place: |
|
Final Designs (plans and specifications). |
Fall 2011 |
Permits (regional water board, El Dorado County, California Department of Fish and Game, Tahoe Regional Planning Agency). |
Spring 2011 |
First Phase Construction |
2012 |
Additional Phases Construction |
Additional 2 - 4 years |
|
|